Commuting in Metro Atlanta

Camp Creek Marketplace Roundabout Open

On August 6, the City of East Point in partnership with the Aerotropolis Atlanta CIDs hosted a ribbon cutting ceremony for the Camp Creek Marketplace Roundabout located at Marketplace Blvd and Shelby Lane.

Design of the roundabout began June 2017 through March 2018 with a design cost of $51,000. Construction began on June 18, 2018. The cost of construction was split in half between the Aerotropolis Atlanta CIDs and the City of East Point for a total of $359,540. The project design converted a 2-way stop into a roundabout to increase the flow of traffic, increase safety, and reduce delays. Further traffic improvements are coming in the spring of 2020 to install a traffic signal upgrade at North Commerce and Redwine.

SOURCE: http://eastpointcity.org/roundabout/